Airport Road project to ‘miss’ third deadline
RAWALPINDI: Third deadline set for completion of Airport Road Expansion project will expire today (Tuesday), making it difficult for contractor to accomplish the project timely, sources said. They said work on a Rs 1.39 billion project was started on February 24, 2007 and was to be completed in 15 months on May 23, 2008. They said deadline was extended till June 30, as the contractor could not complete the project due to pre-monsoon rains. Later, the sources said, the deadline was extended till September 30. Rawalpindi Development Authority (RDA) is yet to acquire possession of the project site, they said. online